PlanitExo · Production planning × Factbird

For Factbird users: how it works

A short overview for those who already use Factbird: what stays the way you are used to, what changes, and how an order goes from the plan to closing. The detailed description is in the full description of Production planning × Factbird.

Approved
01

Factbird stays the measurement, PlanitExo provides the order

If you already use Factbird, measurement and analysis on the production line, stop detection and the OEE calculation stay there. PlanitExo Production planning adds the order data, the plan, and on the tablet the starting, closing and entering of stop reasons. The order reaches Factbird only when production starts, from the latest plan, so the plan can change freely until then and batches do not have to be entered by hand.

02

Terms — who calls the same thing what

FactbirdPlanitExoNote
LineResourceconnected on the Admin → Machines tab
Batchthe blocks of one order stepone batch even when split into any number of blocks
Batch numberbatch identifier fieldan order field copied to the block, today the SAP order number
Item / Productarticle number + namea missing article is created by the upload
Packagingpackaging at the resourceneeded to create a new article
actualStart / actualStop“when the first / last piece came off the line”with a slider, on the tablet
Stop causestop reason (category → reason)the list set up for the line in Factbird
New batch with the same numbercontinuation number|Nthe system appends a sequence number
03

The path of an order from the plan to closing

The planner schedules and freely rearranges the order on the Gantt board, and nothing goes to Factbird yet. At the machine the operator starts it on the tablet (entering when the first piece came off the line), and PlanitExo then uploads and starts the batch from the latest plan. During production the tablet shows Factbird's live piece count and OEE, at the end the operator closes it, and in the planner the block shows the good and scrap pieces produced.

The path of an order on three screens
The whole path on three screens: the Gantt board with the block of an uploaded order, the tablet “Running order (Factbird)” card, and entering stop reasons.
04

Upload at start: always the latest plan

At start the system creates a batch from the data of the block (if the order is not yet in Factbird). The batch identifier is the block-copied value of the order field the admin has designated (today the SAP order number), the quantity is the quantity of the order (or the part falling on the resource), the start is the start of the earliest block, and the speed is 60 divided by the raw cycle time. A missing article is created with the packaging of the machine. A preliminary upload is not needed, and if the order was uploaded in advance and the plan has changed since, starting would start the old version held in Factbird.

05

Starting on the tablet, with the actual start

With the Start order button the operator chooses from a list cut around the shift, and with the “when did the first piece come off” slider gives the real start (Factbird counts pieces from this point). The previous order running on the line is closed at this moment, and on the piece-count check screen the good count from Factbird can be compared with the counter of the machine, and the start corrected afterwards if needed.

Confirm start
The “Confirm start” screen: the selected order and the “When did the first piece come off the line?” slider.
06

Closing and continuing with a numbered batch

When closing, the operator enters the time of the last piece and the manual scrap the sensor does not measure. An order that needs to be continued is never created with a repeated number, but with a sequence number appended (for example 123|1), with the remaining quantity, which is the quantity of the order minus the pieces produced by all variants.

07

Stop reasons on the tablet, with Factbird's list of reasons

The tablet shows the stops without a reason that are longer than a micro stop, from the current and the previous shift, on a timeline and in a list. The operator selects one or more stops, picks the category and the reason from Factbird's two-level list of reasons, and the server checks it against fresh data and records it in Factbird.

Enter stop reasons
The top of the “Enter stop reasons” screen: the shift timeline with the stops without a reason (red) and with a reason.
08

OEE: Factbird's numbers, mapped to four levels

On a Factbird resource the tablet and the dashboard show the four levels from Factbird's time components (Production = TEH1, Changeover = TEH2, Machine = TEH3, Total = total capacity utilisation), matching Factbird's own interface to the decimal for the same time window, but the denominator of the Total level is the full calendar time.

09

Feedback to the Gantt board

On an order block a turquoise mark shows that the data in Factbird matches the plan, and a yellow mark that the plan has deviated since (a modification has to be sent). At the bottom of the block a green-red bar shows the good and scrap pieces produced in proportion to the plan, with the exact numbers in the tooltip.

Good and scrap bar on the Gantt board
Order blocks on the Gantt board: at the bottom of the block the bar of good (green) and scrap (red) pieces produced so far against the plan.
10

What to watch out for

A started or closed batch can no longer be modified from the plan (this is why it is worth leaving the upload to the start). With an empty batch identifier there is no upload (it can be filled in on the block), micro stops do not have to be entered, the two parts of a stop split by production have to be selected separately, the sequence numbering is recognised only in the form |1 … |9, and if Factbird is unreachable the data of the other resources is still shown.